When This Checklist Applies
-
The Nine Checks, In Order
-
Step 1: Write Down What the Part Does in the System, Not What It Looks Like
-
Step 2: Find Out What "Product Centric" Actually Means at This Supplier
-
Step 3: Test the "Login Centric" Portal in the Off Season
-
Step 4: Lock the Drawing, Tolerances, and Material Grade Before You Ask for Pricing
-
Step 5: Ask Who Owns the Tooling — Before You Pay for It
-
Step 6: Request the "Not Included" List, Then Look at the Price
-
Step 7: Treat First Article and PPAP Like a Gate, Not a Formality
-
Step 8: Calculate Rework and Replacement Into Your Landed Cost
-
Step 9: Ask for the Lead Time on This Order, Not the Standard One
-
Step 1: Write Down What the Part Does in the System, Not What It Looks Like
-
What Goes Wrong Most Often
Eight years handling sourcing orders for automotive metal parts — stamped brackets, machined housings, aluminum extrusions, and finished assemblies like a 4-inch muffler delete pipe or the bits inside a piston pump metering system. I've personally made (and documented) six significant mistakes, totaling roughly $41,000 in rework, expedited freight, and one scrapped tool. This checklist would have prevented most of them.
Below are the nine checks I run before I sign a new purchase order, in order. If you're buying anything stamped, machined, forged, or extruded, they apply regardless of who the seller is — a single-process stamper, a die shop, or a multi-process supplier like Centric that runs stamping, CNC, and forging under one roof. None of this is about loyalty to a vendor name.
When This Checklist Applies
Run the full nine when:
- A new supplier is quoting
- An existing supplier is quoting a new part
- You're transferring a part from one vendor to another
- Anyone says the words "basically the same as last time"
If you're simply reordering an identical catalog item, you can skip four of the nine. You'll want the other five anyway.
The Nine Checks, In Order
Step 1: Write Down What the Part Does in the System, Not What It Looks Like
Not the drawing's dimensions. Not the shape. The function.
I got burned on a flywheel in 2021. The drawing was explicit: eight-bolt crank flange, 129-tooth ring gear, 9.8 kg. We made exactly that, and it passed every dimension. First trial assembly, the starter motor meshed badly. Nobody did anything wrong. The ring gear offset differed between our design and the customer's system.
Here's why that matters: a flywheel isn't one function. It stores rotational mass to smooth torque pulses, it provides the starter mesh through the ring gear, and on a manual transmission it also gives the clutch a friction surface. A dual-mass flywheel adds torsional damping on top. If a part does three jobs and the conversation only covered one, something will go wrong.
Ask three questions per part: What does it carry? What does it connect to? What breaks if it fails early? Write the answers down before you request a quote. Costs about twenty minutes. Saved me more than any single tool I use.
Step 2: Find Out What "Product Centric" Actually Means at This Supplier
"Product centric" is one of those phrases from a sales deck. In practice it usually means: deep catalog, plenty of standard stock, fast ordering. For a 4-inch muffler delete pipe with fixed specs, that's genuinely useful. You know what you need, you want it shipped.
For a piston pump metering system housing, it tells you almost nothing. That part is process driven. The bore has to be machined to a specific roundness, the sealing faces finished to a specific surface roughness, and the measurement plan has to be agreed up front. A deep catalog doesn't help you there — engineering support does.
So ask the concrete version: which operations do you run in-house, and which do you subcontract? The answer sorts a vendor into product-centric, process-centric, or broker real fast.
Step 3: Test the "Login Centric" Portal in the Off Season
Every supplier now advertises a customer portal. Of course they do. The pitch: log in, submit the RFQ, track the order, download the inspection files.
The feature list isn't the point. The point is whether it works when nobody is watching. Submit an RFQ yourself on a slow afternoon and time it. If the quote doesn't come back inside a business day, the "login centric" experience is theater — the workflow still runs through a salesperson's inbox. That's not necessarily bad. It just means your timeline depends on one rep, and you should know that before you sign a supply agreement rather than after.
Step 4: Lock the Drawing, Tolerances, and Material Grade Before You Ask for Pricing
Four words that generate the worst quotes: "details to follow, quote it."
More quotes than I care to admit have come back against a sketch, and then drifted eighteen cents a piece by the time the final revision showed up. That's not the supplier being dishonest. That's you asking a machinist to estimate a hole whose tolerance nobody has decided yet.
Your line to the vendor: "The quote should reference drawing revision X, the tolerance table, and material grade." If the respondable version says only "per drawing," park it. Locking this step costs a day. Skipping it cost us a week in 2020, and I'm still annoyed about it.
Step 5: Ask Who Owns the Tooling — Before You Pay for It
Most buyers skip this. Here's something vendors won't volunteer: tooling costs get handled in at least three different ways. Sometimes amortized into the piece price, sometimes invoiced as a line item, and sometimes swallowed into a vague "development charge" with no document saying who holds title.
Ask directly: Who owns the die? If I stop ordering, do you split it, and can you release it back to me? How long does that take? That single answer separates a supplier that's building a five-year relationship from one that's booking a quarterly number.
Step 6: Request the "Not Included" List, Then Look at the Price
I've learned to ask "what's NOT included" before I ask "what's the price." Not because suppliers lie — because build costs are genuinely opaque, and the only party who knows the full set is the one writing the invoice.
The FTC's advertising guidelines require that material claims be substantiated. Hold vendor claims to that same bar. When somebody says "100% inspection" or "zero defects, guaranteed," either produce the evidence or take the phrase off the table. Both outcomes are fine. Ambiguity is not.
The list to run through: tooling, engineering change orders, sample fees, rush fees, freight and handling, packaging upgrades, inspection. Then ask "when does each of these trigger?" on every line. A short list of inclusions isn't a good sign. It's a prompt to keep asking.
Step 7: Treat First Article and PPAP Like a Gate, Not a Formality
I assumed "same as last time" on a 1,200-piece stamping order in 2023. Didn't verify. Turned out the samples came off a die that had been serviced between runs, and the dimensional shift didn't surface until the assembly line. That mistake cost $11,400 between tear-down, rework, and expedited replacement, plus three days of line downtime.
PPAP documentation isn't bureaucracy. It's your only defensible record when a plant manager asks how you validated the process. A supplier who treats it as a signature exercise and hands you paperwork you can't cross-check is doing labeling, not inspection.
Step 8: Calculate Rework and Replacement Into Your Landed Cost
Total cost of ownership means: base part price, tooling, freight, rush fees, inspection, and the expected cost of a rework lot. The lowest quoted number is routinely the highest total number. That's not cynicism — it's arithmetic that most buyers skip because the spreadsheet is annoying to build.
Build it anyway. One page. If a supplier won't give you the inputs to do it, that refusal is itself the answer.
Step 9: Ask for the Lead Time on This Order, Not the Standard One
"Standard turnaround" usually includes buffer time a vendor uses to slot work into the queue. It is not necessarily how long your order takes.
Ask the specific version: for this quantity, from your signature to shipment, how many days? Break it down by operation. If any step is subcontracted, isolate that time separately. In 2022 I accepted "standard 15 days" on a forging run that needed heat treatment. Actual was 23. The eight days were calculable in advance. I just didn't ask.
What Goes Wrong Most Often
Nearly every ordering failure I've documented traces back to one of these:
- Skipping Step 4. Quoting against an unfinished drawing is how you end up renegotiating price after the design freezes.
- Treating the quote as the cost. It's the starting number. Freight and tooling do not appear there.
- Treating the portal as the process. An integrated login screen says nothing about the throughput behind it.
- Assuming "same supplier" means "same lot." It doesn't. Re-verify at the part level.
- Reading "zero defects" as a standard. It's marketing. The only standard is the inspection data attached to the certificate.
I have mixed feelings about this checklist. Running it takes most of a morning, plus three or four vendor emails, and I know people who skip Steps 4 and 8 entirely because "the process is too slow." But a wrong PO has never once cost me hours. It costs weeks, every time. That morning buys back art of the ordering cycle — and it's the cheapest hour of the trade you'll spend all quarter.
If you only adopt one step today, take Step 1. Write down what the part actually does in the system. Everything downstream gets easier once the first question is right.